Construction Updates
I-405 FREEWAY
The southbound I-405 on-ramp from Seal Beach Boulevard is now open. Crews closed the ramp from Seal Beach Boulevard on Feb. 2 to accommodate freeway widening.
Goldenwest I-405 Off-Ramp
Crews closed the southbound I-405 off-ramp to Goldenwest Street/ Westminster Mall Road on Jan. 31 to accommodate the freeway widening.
The ramp is anticipated to reopen this month.
Old Ranch Parkway Closure
Crews closed the Old Ranch Parkway on-ramp to westbound SR-22 on April 13. The ramp closure was extended due to unforeseen site conditions, to address complexities with traffic staging and to accommodate the freeway widening. The ramp is anticipated to reopen in the spring.
SB I-405 Goldenwest Street On-Ramp and Bolsa Avenue Off-Ramp to Close Crews will close the southbound I-405 loop off-ramp to Bolsa Avenue and the southbound I-405 loop on-ramp from Goldenwest Street to accommodate the freeway widening.
The southbound I-405 loop off-ramp to Bolsa is anticipated to close soon for approximately two months. The southbound I-405 loop on-ramp from Goldenwest is also anticipated to close in mid-March for approximately four months. For more information, visit
http:// octa. net. Sign up for project-wide and bridge-specific construction alerts at bit. ly/405-signup.