Pool Progress

Work on the pool continues at a rapid pace. The drywall for the mechanical room and the cement board for interior bathrooms are scheduled to be installed this week.

The final coat of exterior stucco is being applied, and concrete has been poured for the pool deck. Light fixtures have been installed, and prep has started for interior and exterior painting.

The pool has been closed since November 2019, when potentially catastrophic defects were uncovered in the 1960s-era facility.

It is expected to open in early spring. The facility will have a pool with five swimming lanes, a 30-by-30-foot activity area with a volleyball net, a 9-by-25-foot spa, new locker rooms and a lounge area.