Work is ongoing with equipment installation set to begin next week
POOL UPDATE
Work continues at the LW Aquatic Center, which is undergoing a complete renovation. Among recent progress is:
• Rough plumbing and electrical inspection have been completed.
• Preparation for stucco is being prepared.
• Pool decking, along with the area drains, should be completed by Friday, Jan. 28.
• Southern California Edison is on track to complete its section by Monday, Jan. 31.
• Pool equipment is scheduled to start being installed next week. The pool was closed in late 2019 for a simple remodel that mushroomed into a complete redesign and rebuild after catastrophic infrastructure defects were uncovered when work began.
The new facility will include a pool with five swimming lanes, a 30-by-30-foot activity area with a volleyball net, a 9-by-25-foot spa, new locker rooms and a lounge area in a reconfigured space to maximize potential.