Three streets will be paved in September
PAVING PROJECT
The 2023 GRF Paving Project will continue with the paving of five more streets, including Interlachen Road, Twin Hills Drive, South Fairfield Lane, St. Andrews (outside of the gate) and Kenwood Road.
Pedestrians and drivers should proceed with caution and adhere to traffic controls on and near streets that are being paved.
The upcoming schedule of work is as follows:
Interlachen Road
• Asphalt digouts: Aug. 30Sept. 5
• 2-inch grind: Sept. 6-7
• Pave: Sept. 8
• Stripe: Sept. 12-13 Glenview Road
• Concrete Work: Sept. 11-15
•Asphalt digouts: Sept. 18-19
• 2-inch grind: Sept. 20
• Pave: Sept. 22
• Stripe: Sept. 26 St. Andrews Drive (outside of the gate)
• Concrete work and valve adjustment: Sept. 25-29
• Asphalt digouts: Oct. 2-3
• Slurry coat: Oct. 5-6
• Stripe: Oct. 10 Updates on the 2023 GRF Paving Project, including future work dates, will be published in the LW Weekly.