The pool renovation is rapidly progressing as opening day nears.

Crews are continuing to install pool equipment in the mechanical room.

Tile walls are completely grouted.

The flooring contractor will start installing epoxy flooring this week.

Physical Property is still working with SCE to energize the transformer.

The pool has been closed since November 2019, when potentially catastrophic defects were uncovered in the 1960s-era facility.

The project that started as a simple remodel soon morphed into a full-blown reconstruction.

The project coincided with the coronavirus epidemic, which has delayed construction, parts procurement and other facets of the job.

The facility will have a pool with five swimming lanes, a 30-by-30-foot activity area with a volleyball net, a 9-by-25-foot spa, new locker rooms and a spacious lounge area. A grand opening is being planned.