Posted on

Sound wall work starts on North Gate Road

NORTH GATE ROAD

As part of the I-405 Improvement Project, the sound wall on North Gate Road will be replaced.

Crews are scheduled to remove a portion of the old sound wall west of the fire station, beginning as early as Monday, Sept. 13.

Most of the work will take place on weekdays during the day, from 7 a.m.-4 p.m. The road will remain open in both directions; crews will be working behind the concrete barriers.

The job is expected to take approximately three weeks to complete. Sound blankets will be in place until the wall is reconstructed.

The work is part of the I-405 Improvement Project, which will add one regular lane in each direction of I-405 between Euclid Street and I-605, and a second lane in each direction of the freeway from SR-73 and I-605 that will combine with the existing carpool lanes to form the 405 Express Lanes.

To receive updates related to this work and other 405 project construction near Leisure World, visit www.bit. ly/405LeisureWorld.