WORK IS UNDERWAY

WORK IS  UNDERWAY WORK IS  UNDERWAY

POOL CONSTRUCTION

Preliminary construction related to the pool project is underway, with the creation of an ADA path of travel to the pool. Current regulations require the 1960s-era pool to have handicapped parking, which was not a regulation when the facility was built. The job consists of regrading the parking area and creating an opening in the wall bordering St. Andrews Drive to provide safe access to the pool. The GRF Physical Property Committee recommended on May 5 that the GRF Board of Directors award the contract to MJ Jurado to replace the approach from the parking lot to the swimming pool to meet ADA requirements, at a cost not to exceed $44,580. Watch for construction updates as plans are finalized and permits secured to rebuild the pool and spa facility.