Pool Construction Timeline

August 2019: the GRF Board approved renovation of the golf starter area, golf course tees, and pool and locker Rooms

Nov. 4, 2019: Started golf project and pool

Nov. 22, 2019: Engineer reports on condition of pool shell; project on hold.

Feb. 25, 2020: GRF Board approves complete replacement of pool.

Feb. 28, 2020: GRF signed architect’s contract for locker rooms.

June 22, 2020: Pool engineer anticipates long COVID-19-related delay for hydraulic engineering. A new pool engineer is sought.

June 2020: Crews pumped out salt water from the pool; it was caused by ocean encroachment due to a high-water table.

July 13, 2020: Contract agreed to with new pool engineer

Feb. 19, 2021: Plans submitted to plan check.

March 15, 2021: Plan check comments back from City of Seal Beach and Orange County Health Care Agency.

April 2021: Pool design complete, plans resubmitted to City of Seal Beach and Orange County Health Care Agency for final approval.