Nightly closures are set to begin as early as Tuesday, Jan. 19, from 9 p.m.-5 a.m., on weeknights, for approximately two weeks.

Additionally, crews will pour concrete for the Bolsa bridge over the I-405. This work will require a full 12-hour closure of Bolsa between Goldenwest Street and Chestnut Street.

The closure is set for as early as 7 p.m., Monday, Jan. 25, to 7 a.m., Tuesday, Jan. 26.

A detour will be in place for pedestrians and bicyclists to navigate around the closure.

Westminster Boulevard Traffic Shift

Crews will shift traffic to the new Westminster bridge over I-405. The shift will occur in three phases and will require lane reductions.

Eastbound Westminster was reduced to one lane between Springdale Street and Willow Lane, and eastbound traffic was was shifted onto the new bridge Jan. 12.

Crews will be constructing the center median on weekdays and Saturdays for approximately two weeks.

Westminster will then be reduced to one lane in each direction between Springdale Street and Willow Lane from 9:30 p.m., Monday, Jan. 25, to 6 a.m., Tuesday, Jan. 26. Westbound traffic will be shifted onto the new bridge at 6 a.m. Tuesday, Jan. 26.

Crews may mobilize equipment as early as 6 a.m., and some activity may occur at night.

Fairview Road Traffic Shift

Crews also will soon shift traffic to the new half of the Fairview bridge over I-405 and begin working on the second half of that bridge. The traffic shift is set for early-to-mid February and will require bridge and ramp closures.

Demolition of the second half of the bridge will occur over two weekends, under full freeway closures and is set for late February.

The 405 Community Outreach Team will provide detailed schedule, closure, detour information in future alerts.

Off-Ramp to Beach Boulevard is PERMANENTLY CLOSED

The southbound I-405 loop off-ramp to northbound Beach Boulevard is permanently closed. Motorists will use the Beach Boulevard/ Center Avenue off-ramp from now on to access north- and southbound Beach Boulevard.

The loop off-ramp was eliminated to accommodate the widening of Beach and of the freeway. The Beach/Center off-ramp and Center are being reconstructed to accommodate the change in traffic volume.

Email 405project@octa.net or call (888) 400-8994 for more information. The I-405 Improvement Project mobile app provides quick access to current traffic conditions, closures and detours, along with project updates and links to contact the project team. Download it from the Apple Store or Google Play.