Posted on

Sewer line project is moving along

OC SANITATION DISTRICT

The Orange County Sanitation District has installed a 2-mile stretch of sewer pipeline in the City of Seal Beach to improve the regional system. Construction is ongoing on Westminster Boulevard between Seal Beach Boulevard and Bolsa Chica Road. The project will move into the City of Westminster with pre-construction activities anticipated to start after the Thanksgiving holiday.

Upcoming Construction Schedule Starting Nov. 30, pre-construction activity will begin. That includes restriping traffic lanes at night followed by installing k-rail concrete barriers during the day to accommodate construction within the center median area.

Starting Dec. 3, utility investigation, or potholing, will occur in the intersection of Bolsa Chica Road and Westminster Boulevard at night.

Day work hours are from 7

SEWER, page 23 a.m.-7 p.m., Monday-Friday; night work is between 9 p.m.-6 a.m., Monday-Friday.

During non-construction work hours, two lanes of travel in each direction will be open. Expect periodic traffic delays and reduced travel lanes during non-peak traffic hours For more frequent updates, sign up to receive e-mail notifications and/or text alerts, sign up at www.ocsd. com/Westminster. The Construction Hotline is available at (714) 378-2965. For project details, visit www.OCSD.com/westminster.

Leave a Reply

Your email address will not be published. Required fields are marked *

LATEST NEWS