LW POOL Progress on ….
LW POOL
Progress on the pool project continues despite challenges posed by COVID-19. The coordination of plans from the architect and pool engineer is underway. Work continues on the underground plumbing. The finished facility will include a five-lane pool, a 30-by-30-foot activity area with a volleyball net, a 9-by-25-foot spa, new locker rooms and a lounge area in a reconfigured space to maximize its potential. The pool depth will be 5 feet in the deep end.
PAVING PROJECT
The 2020 Trust Street Paving project will run through October. Grind and overlay projects are ongoing around LW. The parking lots at clubhouses 3 and 4 are being slurry sealed. Drivers are asked to obey construction zone signs, speed limits and flagmen during construction.
FITNESS CENTER
The installation of new equipment is nearly complete with the unveiling of the new Fitness Center scheduled for next week. Dedicated fitness areas include a flex-and-stretch zone, a free weight area and two strength circuits, plus a “smart” group fitness room. A barre for dance groups has been installed. Smart upgrades include an Echelon Smart Connect Fitness Mirror, which provides an interactive workout experience through the device.
KNOWLEDGE & LEARNING CENTER/TEST KITCHEN
The new Knowledge and Learning Center in Rooms 9 and 10 of Clubhouse 3 is 99 percent complete and has been used for staff training.
The center features computer stations, state-of-the-art audiovisual equipment, assistive listening devices, a “smart” board and two 80-inch monitors.
The demonstration kitchen project is tentatively scheduled for completion at the end of October. Tile work is finished and cabinets are being installed.
The space will be used for cooking classes and hosting parties for which residents can cook for themselves.